Idea + Execution + Timing = Success

PMP Exam: Part – 8

Think about these kind of questions ….When I started my hand written notes, I thought how a question can be framed on a topic. I would sometimes ignore which were direct but would think about the cumulative questions as shown below. Try to frame questions on topics discussed in the LL’s in this forum; If [...]

readmore

PMP Exam: Part – 7

Start of project ————————————————–>> Closing Risk – High ——- Decreases as project progresses Uncertainity -High ——- Decreases as project progresses Ability to make changes by SH’s -High Cost -low ————- Increases, constant and decreases. Impact-low ————- Increases as project progresses. CV (-) , SV(+) —> crash CV(+) , SV(-) —-> Not enough resources applied Cost [...]