More pointers : – Your Director calls you and asks you for an estimate on the phone. You have done similar project before. What type of estimating would you use? – How would addition of costs/resources impact CPI/SPI ? Look at the equation. – During the life cyle of a project, where is Quality, scope […]
Here are the formula’s to remember: Slack/Float = Critical Path – Sum (Duration of that Path) ES = Sum of Predecessors +1 EF = ES +Duration -1 LS = ES + FLOAT (Remember FLOAT = LS- ES which is a transpose of LESS) LF = LS+Duration-1 Dummy activity has zero duration PV = %Complete x […]